Clarification Required on Resource Allocation and Migration Plan

Asslamulaikum,

As per our initial requirement, we requested infrastructure resources for the BEZA OSS environment, and we appreciate the resources provisioned by NDC, including the compute and storage allocation across DC and DR, which appear sufficient for our deployment.

image.png

We have got 200 Cores , 400GB Ram, And 10000GB storage from NDC.

image.png

However, we would like clarification regarding the PostgreSQL database configuration, specifically the CPU allocation

image.png

Additionally, we are planning to migrate approximately 400 GB of static files. With the currently provided minimal bastion server, we are concerned about potential bandwidth and performance limitations during the migration process. We kindly request guidance or recommendations for an efficient and secure approach (e.g., temporary resource enhancement or alternative transfer method) to complete the migration within the planned window.

We would appreciate your clarification and support on the above matters so that we can proceed smoothly with the migration and deployment activities.